Budgets and variancesPlanning the money, then checking what really happened

Before a business spends a single dollar it should have a plan. A baker in Freetown who buys flour without knowing how much she can afford may run out of cash before the month ends. A budget is that plan in numbers: how much money the business expects to earn and spend in a future period. In this lesson you will follow one question: how does a business plan its money and decide whether a big purchase is worth it?

Budget: a financial plan for a future period that sets targets for income and spending. Variance: the difference between the budgeted figure and the actual figure. Variance analysis: studying variances to find out why plans and results differ, and what to do about it.

Budgets do four jobs. They set targets that staff can aim for, control spending by giving each department a limit, coordinate departments so that marketing does not spend what production needs, and give a yardstick to measure performance at the end of the period. Each budget has a budget holder, the manager who is responsible for keeping to it. Schools in Sierra Leone, hospitals in Texas and start-ups in Lagos all use them.

Reading a variance

A variance is found by comparing actual with budget, and the sign tells you the effect on profit. If the result is better for profit than planned, the variance is favourable (F). If it is worse for profit, it is adverse (A). The same number can be favourable or adverse depending on whether it is revenue or cost, so always ask: is this good or bad for profit?

ITEMBUDGETACTUALVARIANCE Sales$5,000$4,600−$400 A Materials$1,800$2,000−$200 A Labour$1,200$1,100+$100 F PROFIT$2,000$1,500−$500 A

Read the table from the baker's point of view. Sales were $400 short (adverse). Materials cost $200 more than planned (adverse, because higher cost lowers profit). Labour cost $100 less (favourable, because lower cost raises profit). Add the effects: −400 − 200 + 100 = −$500, which is exactly the profit variance. Managers then ask why: perhaps a flour price rise caused the materials variance, and a rainy week cut customers.

Activity 1 · Foundations: the language of budgets
Activity 2 · Quick check: budgets and variances
Exam trap. Do not label a variance "adverse" just because the number is bigger or smaller. A cost that is higher than budget is adverse. A revenue that is higher than budget is favourable. Always judge the effect on profit. Examiners also reward a short reason, such as "adverse because suppliers raised prices".

A quick recap: break-even

You met break-even in the lesson on costs and revenues. It is the output at which total revenue equals total cost: fixed cost ÷ (price − variable cost per unit). Budgets and break-even work together. A manager budgets sales, compares them with the break-even output, and checks the margin of safety (budgeted sales minus break-even sales). A big margin means sales can miss the budget and the firm still avoids a loss.

⏱️

Investment appraisal: payback and ARRIs a big purchase worth it? Two simple tests

Sometimes a business must spend a large sum now in the hope of earning more later: a new oven, a delivery van, a second shop. This is an investment, and the process of judging whether it is worth the money is investment appraisal. The risk is real. If Kwame's workshop buys a $10,000 machine that never earns its cost back, the loss can sink the business. So managers estimate the net cash flow each year (cash coming in minus cash going out) and then test the project with one or more methods.

Investment appraisal: judging whether a major spending project is worth doing by comparing its expected returns with its cost. Net cash flow: cash inflows minus cash outflows in a period. The three standard methods are payback, average rate of return (ARR) and net present value (NPV).
⏱️PAYBACKHow fast do we get ourmoney back?time until cash in = costEasy, but ignores later cash 📈ARRWhat % do we earn eachyear, on average?average yearly profit ÷ costCompare with interest rates 💰NPVWhat is the future cashworth in today's money?PV of inflows − costBest method, harder sums
Activity 3 · Appraisal terms

Payback period

The payback period is the length of time it takes for a project's cash inflows to repay its cost. Add the yearly net cash flows until the total reaches the cost. If it does not land exactly on a year end, use a fraction: full years + (cost still to recover ÷ cash flow of the next year) × 12 months. A manager compares the result with a target, for example "we only accept projects that pay back within 3 years". Shorter is better, because less time means less risk and a quicker return of cash to the business.

Advantages: simple to calculate and understand, and good for a firm short of cash or worried about risk. Disadvantages: it ignores all the cash that arrives after the payback date, and it ignores the time value of money, the idea that cash received sooner is worth more.

Average rate of return (ARR)

ARR measures the average yearly profit from a project as a percentage of the amount invested.

The ARR steps

1. Add up all the cash inflows over the life of the project.
2. Subtract the cost: this is the total net return.
3. Divide by the number of years: the average annual return.
4. ARR = average annual return ÷ initial cost × 100.
A manager then compares ARR with the interest rate on a bank loan or with a target. If a loan costs 8% and the project's ARR is 16%, it looks attractive.

Advantages: uses all the cash flows and gives a percentage that is easy to compare. Disadvantages: it still ignores the timing of the cash, so $5,000 in year 1 counts the same as $5,000 in year 5.

Try it: a project with a changing price tag

A workshop in Bo may buy a machine. It is expected to bring in net cash of $3,000, $4,000, $5,000, $4,000 and $2,000 over five years (total $18,000). The firm's rule is to accept a project only if it pays back in 3 years or less. Slide the cost of the machine and watch the bars: blue bars show the cash collected so far, and a bar turns green once the cost has been recovered.

Cost Y1Y2Y3Y4Y5YearCash collected
Payback2 yrs 7 mo
ARR16.0%
Net return$8,000

Move the slider

Activity 4 · Change the cost at least three times, and find one cost the firm would accept and one it would reject, to complete this activity.

Exam trap. Payback is a time, not a sum of money, and ARR is a percentage, not dollars. Show your working and give the unit: "2 years 7 months" or "16%". Also remember that ARR divides the average yearly net return by the initial cost, not by the total inflows.
🪙

Discounting and net present valueWhy $1,000 tomorrow is worth less than $1,000 today

Offer a student $100 today or $100 in three years. Almost everyone chooses today. Why? Cash today can be saved or invested to earn interest, it is safe (the future is uncertain), and in many countries inflation means the same dollar buys less later. This is the time value of money, and it is the weakness that payback and ARR ignore. Net present value (NPV) fixes it by converting every future cash flow into its value today.

Discounting: reducing the value of future cash to find its worth today, using a discount rate (often the interest rate or the return the firm could earn elsewhere). Present value (PV) of a cash flow = cash flow ÷ (1 + r)t, where r is the discount rate and t the number of years. NPV = total present value of inflows − initial cost.
$100.00Today $90.91In 1 year $82.64In 2 years $75.13In 3 years Value today of $100 received later, discounted at 10% a year

The bars show it clearly. At a 10% discount rate, $100 received in three years is worth only $75.13 today: 100 ÷ 1.13 = 100 ÷ 1.331. The later the cash, the more it is shrunk. A higher discount rate shrinks future cash even more, so it is harder for a project to pass.

Calculating NPV

The NPV steps

1. Choose a discount rate r.
2. For each year t, divide that year's net cash flow by (1 + r)t (or multiply by the discount factor from a table).
3. Add the present values.
4. Subtract the initial cost. The answer is the NPV.
Decision rule: NPV above zero means the project earns more than the discount rate, so accept it on financial grounds. NPV below zero means reject it. If choosing between projects, prefer the one with the higher NPV.

Advantages: it uses all the cash flows and respects the time value of money. Disadvantages: the sums are harder, and the answer depends on a discount rate that is only an estimate. Forecast cash flows can also be wrong, especially in later years.

Try it: raise the discount rate

Ngozi's bakery will spend $10,000 on a new oven. It is expected to bring net cash of $4,000 in year 1, $5,000 in year 2 and $6,000 in year 3. Slide the discount rate. The grey bars show the cash, and the teal bars show what each year's cash is worth today.

Year 1Year 2Year 3CashPresent valueDollars
PV year 1$3,636
PV year 2$4,132
PV year 3$4,508
Total PV$12,276
Cost$10,000
NPV$2,276

Move the slider

Activity 5 · Change the rate at least three times, and find a rate where NPV is positive and one where it is negative, to complete this activity.

Exam trap. Year 1 cash is divided by (1 + r) once, year 2 by (1 + r)2, and so on. Cash spent today (the cost) is not discounted. Do not forget to subtract the cost at the end: the sum of present values alone is not the NPV. If you use a table of discount factors, your answer may differ by a few dollars from an exact calculation because the factors are rounded. That is accepted.
🧭

Beyond the numbersQualitative factors and making the final choice

If every decision followed the highest NPV there would be no need for managers. In reality the numbers are only forecasts, and some of the most important facts cannot be measured in dollars. Quantitative factors are the figures: cost, payback, ARR, NPV. Qualitative factors are the judgements that affect whether the investment really succeeds.

THEDECISION Risk anduncertainty Market andcompetition Environmentand waste Ethics and thelocal community Staff skillsand morale Brand andreputation

Here are examples. A new factory may have a high NPV but pollute a river, harming the firm's reputation and risking fines. A new product may look profitable but may need skills the staff do not have, hurting morale. A project may be cheap but depends on a country with an unstable government, which is a risk. Cutting corners on ethics, for example by using suppliers who treat workers badly, can cost sales when customers find out. Good managers combine the numbers with these judgements.

Activity 6 · Sort: quantitative or qualitative factor?

Choosing a method

No single method is perfect, so firms often use more than one. A cash-poor start-up in Accra may put payback first because it needs its money back fast. A large firm planning a ten-year plant will prefer NPV because the timing of cash matters over a long life. A manager comparing a project with a bank deposit may look at ARR. In the exam, you are rewarded for choosing a method and justifying it with a reason that fits the business in the question.

Quick comparison

Payback: measures time, ignores later cash and timing.
ARR: measures a percentage, uses all cash but ignores timing.
NPV: measures a dollar value today, uses all cash and timing, but needs a discount rate.
All three depend on forecasts, which can be wrong.

🧮

Put it to workWorked examples, then your turn

Worked example 1 · Variances

Question. A shop budgets sales of $20,000 and costs of $15,500. Actual sales are $21,200 and actual costs are $16,400. Calculate the sales variance, the cost variance and the profit variance, and say whether each is favourable or adverse.

Solution. Sales: 21,200 − 20,000 = $1,200 favourable (more revenue). Costs: 16,400 − 15,500 = $900 higher, so $900 adverse. Budgeted profit = 20,000 − 15,500 = $4,500. Actual profit = 21,200 − 16,400 = $4,800. Profit variance = $300 favourable. Check: +1,200 − 900 = +300.

Worked example 2 · Payback and ARR

Question. A project costs $10,000 and brings net cash of $3,000, $4,000, $5,000, $4,000 and $2,000 in years 1 to 5. Calculate the payback period and the ARR.

Solution. Payback: cumulative cash is $3,000, $7,000, $12,000. After 2 years $3,000 is still to recover, and year 3 brings $5,000, so 3,000 ÷ 5,000 = 0.6 of a year ≈ 7 months. Payback = 2 years 7 months. ARR: total inflows = $18,000; net return = 18,000 − 10,000 = $8,000; average per year = 8,000 ÷ 5 = $1,600; ARR = 1,600 ÷ 10,000 × 100 = 16%.

Worked example 3 · Net present value

Question. A bakery spends $10,000 on an oven. Net cash is $4,000, $5,000 and $6,000 in years 1 to 3. The discount rate is 10%. Calculate the NPV.

Solution. Year 1: 4,000 ÷ 1.10 = $3,636. Year 2: 5,000 ÷ 1.21 = $4,132. Year 3: 6,000 ÷ 1.331 = $4,508. Total PV = $12,276. NPV = 12,276 − 10,000 = $2,276. It is positive, so accept on financial grounds. (With the table factors 0.909, 0.826 and 0.751 you would get about $2,272, which is also accepted.)

Activity 7 · Your turn: calculations

Type numbers only. No units, commas or dollar signs.

Key terms

Budget: plan for future income and spending
Variance: actual minus budget
Adverse: worse for profit than planned
Favourable: better for profit than planned
Payback: time to recover the cost
ARR: average yearly return ÷ cost
Discounting: shrinking future cash to today's value
NPV: PV of inflows minus cost
✍️

In the exam roomThree exam-style questions with mark schemes

Open each question, write your own answer on paper first, then compare. Every answer shows why marks are gained and why marks are lost. These match the style of WASSCE, Cambridge IGCSE and O Level, IB and AP questions.

Question 1 (4 marks). Define a budget [2]. Explain one benefit to a business of using budgets [2].

Mark scheme

A budget is a financial plan [1] for a future period that sets targets for income and spending [1]. One benefit: it controls spending [1], because each department has a limit, so managers notice overspending early and can act before cash runs out [1]. Other accepted benefits: setting targets, coordinating departments, or measuring performance by comparing with actual results.

Why marks are lost: writing that a budget is "money for the business" (it is a plan, not a sum); naming a benefit without explaining how the budget produces it; confusing a budget with a forecast of what will happen rather than a target of what is planned.

Question 2 (6 marks). A café budgets sales of $12,000 and costs of $9,000 for a month. Actual sales are $10,800 and actual costs are $9,300. (a) Calculate the sales variance and state whether it is adverse or favourable [2]. (b) Calculate the cost variance and state whether it is adverse or favourable [2]. (c) Calculate the profit variance [2].

Mark scheme

(a) 12,000 − 10,800 = $1,200 [1], adverse because sales are below budget [1]. (b) 9,300 − 9,000 = $300 [1], adverse because costs are above budget [1]. (c) Budgeted profit = 12,000 − 9,000 = $3,000; actual profit = 10,800 − 9,300 = $1,500 [1]; profit variance = $1,500 adverse [1]. Check: 1,200 + 300 = 1,500.

Why marks are lost: calling the cost variance favourable because the number is positive; forgetting to say adverse or favourable; giving the actual profit ($1,500) instead of the variance; subtracting in the wrong direction and ending with a figure that does not match the check.

Question 3 (9 marks). A firm is considering a machine that costs $50,000. Net cash inflows are $10,000, $20,000, $25,000 and $15,000 in years 1 to 4. (a) Calculate the payback period [2]. (b) Calculate the average rate of return [3]. (c) Explain one limitation of the payback method [2]. (d) Explain one qualitative factor the firm should consider before deciding [2].

Mark scheme

(a) Cumulative cash: $10,000, $30,000, then $55,000 in year 3. After 2 years $20,000 is still to recover [1], and 20,000 ÷ 25,000 = 0.8 of year 3, so payback ≈ 2.8 years (2 years 10 months) [1]. (b) Total inflows = $70,000, so net return = $20,000 [1]; average per year = 20,000 ÷ 4 = $5,000 [1]; ARR = 5,000 ÷ 50,000 × 100 = 10% [1]. (c) It ignores the cash received after the payback date [1], so a project with large later returns could be wrongly rejected [1]. Accepted alternative: it ignores the time value of money. (d) For example, the effect on staff morale [1]: if the machine replaces workers, morale and productivity may fall, which could reduce the benefits the forecasts assume [1]. Other accepted factors: environmental impact, reputation, risk, or competitors' reactions.

Why marks are lost: dividing by total inflows ($70,000) instead of the initial cost in ARR; forgetting to subtract the cost to get net return; writing payback as dollars; naming a factor such as "NPV" which is quantitative, not qualitative; giving a limitation without saying what it causes.

Four mistakes that cost the most marks. (1) Calling a variance adverse or favourable without checking the effect on profit. (2) Mixing up payback (time) and ARR (percentage). (3) Using total inflows instead of net return when working out ARR. (4) Forgetting to subtract the initial cost when finding NPV, or discounting the cost itself.
✅

CheckTest the whole lesson

Activity 8 · Mixed check

Take your time and read every option.

🃏